FAQ
Questions and answers
Answers to frequently asked questions about business solar, construction, equipment, and financing.
General
Costs, timelines, and permits
The cost depends on capacity, installation type, equipment, and configuration. Indicative prices range from UAH 300,000 for small sites to several million for businesses. Contact us for a free preliminary estimate.
From the start of design to commissioning, usually 2–4 months. Installation at a prepared site after documentation approval takes 2–6 weeks, depending on capacity.
Up to 50 kW, a simplified process applies without a construction permit. From 50 kW, DTEK approval and technical connection conditions are required. We support the entire permitting process.
Technical
Capacity, roofing, and equipment
The minimum practical capacity for a commercial site starts at 30–50 kW. However, the best solution depends on actual consumption and the load profile.
We inspect the roof before installation. If it needs repairs, these should be completed before the system is installed. An engineer also checks the structure's load-bearing capacity.
BESS (battery energy storage system) consists of industrial batteries that store electricity for use during peak hours or outages. It is recommended for sites with uneven consumption or a need for autonomy.
Financial
Payback, loans, and grants
The average payback period is 3–6 years, depending on the tariff, capacity, consumption profile, and financing. With a tariff of UAH 5/kWh and self-consumption above 70%, payback is closer to 3–4 years.
Yes. We work with several bank programmes. Some clients obtain financing with a 20–30% down payment and a 5–7-year loan. In some cases, the loan payment is lower than the monthly savings.
Some international organisations offer programmes, particularly for agriculture and small businesses. We help you understand the current opportunities for your site.
Useful sections
Where to find more details
Calculate your project today
Get a free energy-consumption analysis and a preliminary solar or battery storage estimate for your site.
- Response within 2 hours
- Free preliminary estimate
- Dedicated engineering consultant
- No-obligation consultation